1. Name 2 of the 5 items that are inputs to the function-point estimating method. (1 point for both parts of answer. ½ point for 1 part of answer.)

 

·       Inputs

·       Outputs

·       Inquiries

·       Logical internal files

·       External interface files

 

2. Name 3 reasons for overly optimistic scheduling. (1 point for 3 parts of answer. ½ point for 1 or 2 parts of answer.)

 

·       External immovable deadline.

·       Making plans based on best-case estimate.

·       Deliberately underestimate because workers like the pressure.

·       In order to submit a winning bid.

·       To get funding for a project.

·       To force developers to work harder.

·       Feature creep. Features added to an initially realistic schedule.

·       Poor estimating.